| Connection | Change | Status |
|---|---|---|
FaTMAN link to SuperJANET 4 |
Upgrade connection from 30Mbps to 622Mbps | Completed and in full service |
University of Abertay Dundee |
Upgrade connection to 1Gbps | Complete |
University of Dundee |
Upgrade connection to 2Gbps | Completed |
University of St Andrews |
Upgrade connection to 1Gbps | Completed Will later operate at 2Gbps |
Create new Point of Presence at Kirkcaldy |
Connection at 155Mbps | Completed |
Angus College |
Upgrade connection to 100Mbps | Completed |
Dundee College |
Upgrade connection to 100Mbps | Completed |
Elmwood College |
Upgrade connection to 100Mbps | Completed |
Fife College |
Upgrade connection to 100Mbps | Completed |
Glenrothes College |
Upgrade connection to 100Mbps | Completed |
Lauder College |
Upgrade connection to 100Mbps | Completed (including transfer from EaStMAN) |
Thus plc have been selected as the main provider of communication circuits.
Stiell networks of Uddingston are the main contractors for the supply of network equipment. This is mostly Cisco Systems products
All work is being managed by University of Dundee IT Services on behalf of the FaTMAN Consortium.
Substantial funding for this upgrade has been provided by SHEFC and SFEFC.